Banner

Case Study - Turn Key Installation

Titan Tanks and Vessels was awarded a turn-key contract by Rising Star Energy, LLC., to provide storage tanks, separators and all the required installation and hook up. Allied Technology is unique among our competitors in our ability to provide both equipment and installation through our roustabout division as a single source so that delays are minimized and production is initiated as soon as possible.

The photos illustrate our roustabout and installation progress from arriving at the site until hook up was completed. The entire installation and hook up of the tank battery and separators took only 7 ½ hours resulting in reduced time for the client to recognize revenue from production. Quality equipment, delivery, safety and rapid turn-key installation services separate Allied Technology from our competitors.